Steps
- 1Verify installation against stamped design before energization tests
- 2Run test sequence per spec: continuity, insulation, polarity, then live tests
- 3Record string-level baselines — they're your degradation reference forever
- 4Punch-list every deficiency with owner + deadline before turnover
- 5Training handoff to O&M includes docs, credentials, and monitoring walkthrough
- 6Archive commissioning package searchable by future troubleshooting
Common Pitfalls
- ▲Energizing on partial inspections under schedule pressure
- ▲String baselines never recorded, degradation unknowable
Commands
Install with skills CLI
$ npx skills add aniruddhaadak80/skills --skill project-development-commissioning-checklistInstall globally
$ npx skills add aniruddhaadak80/skills --skill project-development-commissioning-checklist -gTags
#commissioning#quality#handover#energy-renewables#project-development